New LED lights being fitted across Liverpool

Between February and October 2018, 15,000 new LED 'white light' energy saving bulbs will be fitted in street lights across the city as Phase Two of a major £7m upgrade.

Phase One of the programme was completed in 2017 and saw 12,000 lights changed in 1,800 streets, reducing carbon emissions by 1,500 tonnes and saving the city more than half a million pounds.

Phase Two will cut the council’s energy bill by a further £260,000 a year, reduce carbon emissions by about 1,300 tonnes (saving £21,000) and reduce our street light maintenance bill by approximately £47,000 a year.

In total, maintenance costs will also reduce by £2.7m over the next five years, once all the street lights have been converted.

This work is being carried out in partnership SSE Enterprise.

When and where is the work happening?

Please see the tables below for Phase Two of the work taking place in residential areas and along major traffic routes in Liverpool.

The work begins in February 2018 and ends in October 2018. All dates are subject to change.

Residential areas
Area/Ward Proposed start date Proposed finish date
Croxteth 19/02/2018 12/04/2018
Yew Tree 13/04/2018 02/05/2018
Norris Green 03/05/2018 16/05/2018
Knotty Ash 17/05/2018 24/06/2018
Old Swan 25/05/2018 12/06/2018
West Derby 13/06/2018 25/06/2018
Clubmoor 26/06/2018 09/07/2018
Anfield 10/07/2018 18/07/2018
Tuebrook and Stoneycroft 19/07/2018 06/08/2018
Kensington and Fairfield 07/08/2018 15/08/2018
Picton 16/08/2018 31/08/2018
Wavertree 03/09/2018 17/09/2018
Childwall 18/09/2018 27/09/2018
Belle Vale 28/09/2018 09/10/2018
Woolton 10/10/2018 31/10/2018
Speke and Garston 01/11/2018 22/11/2018
Traffic routes in Liverpool
Route Proposed start date Proposed finish date
Kensington/Prescot Road/East Prescot Road 03/05/2018 01/06/2018
Longmoor Lane 04/06/2018 04/06/2018
Breeze Hill 05/06/2018 05/06/2018
Barlows Lane 06/06/2018 06/06/2018
Rice Lane 07/06/2018 13/06/2018
Liver Industrial Estate 14/06/2018 15/06/2018
Leyfield Road/Town Row 18/06/2018 20/06/2018
Mill Bank /Rocky Lane/West Derby Road 21/06/2018 09/07/2018
Green Lane 10/07/2018 13/07/2018
Shiel Road 16/07/2018 18/07/2018
Atwell Street 19/07/2018 19/07/2018
Severs Street 20/07/2018 20/07/2018
Belmont Road 23/07/2018 24/07/2018
Boundary Lane 25/07/2018 25/07/2018
Heyworth Street 26/07/2018 27/07/2018
St Domingo Road 30/07/2018 31/07/2018
Commercial Road 01/08/2018 02/08/2018
Lambeth Road 03/08/2018 03/08/2018
Melrose Road 06/08/2018 07/08/2018
Selwyn Street 08/08/2018 09/09/2018
Queens Drive 10/08/2018 15/08/2018
Brewster Street 16/08/2018 16/08/2018
Walton Breck Road 17/08/2018 22/08/2018
Townsend Avenue 23/08/2018 24/08/2018
Aigburth Road/St Mary's Road 27/08/2018 14/09/2018